Main Contract Work Plan
Schedule of outputs:(Project month 1 = 02/2003) 
The Main Contract activities on institutional and policy issues have been developed during the four years forecasted for the gradual implementation of the Project through the preparation and implementation of commonly agreed measures.
Six main Outputs had to be achieved between February 2003 and January 2007, each Output being developed, published or adopted according to the correct schedule. All the requested publications, reports, events and trainings foreseen in the Main Contract have been achieved.
Output 1, the Diagnostic Study, has been designed during years 1 and 2. It was then updated and published during the third quarter of year 4.
Output 2, the Blue Paper and the Regional Transport Action Plan, have been developed over years 2 to 4. An update is expected at the end of year 4.
The same applies to Output 3, Studies and Special Studies, which have been published during year 2 and at the end of year 4.
Output 4, Policy Dialogue and Output 6, Information and Dissemination, are ongoing processes being developed at national, regional and Euro-Mediterranean level. They were fully developed during years 3 and 4 of the Project.
 |
 |
|